Salt Lake City Airport Expansion Complete: A Full Breakdown of the Finished New SLC
The Salt Lake City airport expansion is complete. After 12 years of construction and $5.1 billion, the last seven gates and six new restaurants and shops of The New SLC opened on Oct. 27, 2026. The finished airport has 94 gates, 101 concessions and one central terminal with two long concourses.
Here's the full breakdown: what opened Oct. 27, where to eat, what the money built, how long it took and how to get there.
THE SIX NEW RESTAURANTS AND SHOPS

Let's start with the food. Six new concessions opened Oct. 27, all on Concourse B-east, in a mix of local and national brands:
- Einstein Bros. Bagels
- Monarca
- Moochie's Cheesesteaks
- Mr. Charlie's Chicken Fingers
- Swig
- &Go SLC: a news and convenience retail store.
With these six, the airport reaches 101 concessions in total. The airport's fact sheet says all concessions at The New SLC have street pricing.
WHAT OPENED OCT. 27: CONCOURSE B-EAST

The final section of Concourse B-east is about 132,000 square feet. It adds seven gates: five for United Airlines and two common-use gates that other airlines serving SLC can use as needed. The airport also built out the first level of B-east for a future hardstand operation with concessions and gate seating, which will be activated as new air service needs more gates.
The project wrapped up with a celebration on Saturday, Oct. 24. Utah composer Kurt Bestor premiered an airport theme, "Lux Altior" ("The Higher Light"), and the airport unveiled "Crossroads to the World," a suspended art installation of about 2,500 colorful, laser-cut acrylic airplanes, according to the airport.
THE NEW SLC BY THE NUMBERS
| At a glance | Details |
|---|---|
| Total cost | $5.1 billion |
| Construction | July 2014 to Oct. 27, 2026 (12 years) |
| Gates | 94, including 6 international gates, plus 4 hardstand positions |
| Concessions | 101 |
| Layout | One central terminal and two linear concourses (replacing three aging terminals) |
| New facility footprint | 296.7 acres |
| Built for | 34 million passengers |
| Parking garage | 3,600 stalls |
| Workforce | About 25,000 craft workers, 18 million+ craft hours |
| Green building | LEED Gold |
How the money was paid
The airport is an enterprise fund of Salt Lake City and says it is financially self-sustaining. Per its fact sheet, no local tax dollars were spent on The New SLC. Funding came from airport funds, passenger and customer facility charges, airport revenue bonds, federal grants and future bonds.
The terminal and concourses
The old airport had three aging terminals. The New SLC replaced them with one central terminal and two linear concourses, A and B, connected by tunnels. The fact sheet says the linear layout is about 30% more efficient because it cuts taxi times and aircraft idling. The project also includes the parking garage, an elevated roadway and a rental car service facility.
WHO LED IT AND HOW LONG IT TOOK
The Salt Lake City Department of Airports built The New SLC, led by executive director Bill Wyatt. At the celebration, Salt Lake City Mayor Erin Mendenhall called it "the first new hub airport built in the United States in the 21st century."
| When | Milestone |
|---|---|
| July 2014 | Ground broken on The New SLC |
| Sept. 2020 | Phase 1 opens |
| Oct. 2023 | Phase 2 opens |
| Oct. 2024 | Phase 3 opens |
| July 14, 2026 | Four more gates open |
| Oct. 24, 2026 | Completion celebration |
| Oct. 27, 2026 | Final seven gates and six concessions open |
Along the way, nearly 25,000 craft workers put in more than 18 million craft hours. Since the first phase opened, the airport has also been named Best Airport in North America in the large-hub category by Airports Council International.
GETTING TO THE AIRPORT
- TRAX: The Green Line airport station is on the ground level on the east side of the terminal (exit door 1A and head east). A one-way fare is $2.50.
- Parking (per 24 hours): long-term economy $14 with a free shuttle, daily garage $45, premium reserved $65.
- Driving: an elevated roadway serves the terminal, with the parking garage between the terminal and the economy lots.
GROWTH AROUND THE AIRPORT
The land around the airport, called the Northwest Quadrant, is a focus of state and city planning. The Utah Inland Port Authority and Salt Lake City presented a Northwest Quadrant baseline study and recommendations in March 2026. In May 2026, the authority approved $500,000 to help move a rail yard out of the Poplar Grove neighborhood to a new interchange south of the airport, a project that aims to reduce blocked rail crossings and improve traffic flow on the west side.
WHAT IT MEANS IF YOU LIVE OR MOVE NEARBY
For anyone relocating to Utah or weighing a move in west Salt Lake City, North Salt Lake or Davis County, a finished airport with a TRAX connection is a real day-to-day convenience, and the west-side rail project aims to reduce blocked rail crossings and improve traffic flow on the west side. Commute and access matter, so test your drive or train ride at the times you'd actually travel. For current prices in any area, a Red Sign agent can pull local numbers for you.
FAQ
Is the Salt Lake City airport expansion complete?
Yes. The airport celebrated the completion of The New SLC on Oct. 24, 2026, and the final section of Concourse B-east, with seven gates and six concessions, opened to the public on Oct. 27, 2026.
What new restaurants opened at the SLC airport?
Six new concessions opened on Concourse B-east on Oct. 27, 2026: Einstein Bros. Bagels, Monarca, Moochie's Cheesesteaks, Mr. Charlie's Chicken Fingers, Swig, and &Go SLC, a news and convenience store.
How many gates does the new SLC airport have?
At completion, The New SLC has 94 aircraft gates, plus four hardstand positions, and 101 concessions. Six gates are international gates.
How much did the new Salt Lake City airport cost?
The New SLC cost $5.1 billion. The airport says it is financially self-sustaining and that no local tax dollars were spent on the project.
Can I take TRAX to the Salt Lake City airport?
Yes. The TRAX Green Line stops at the airport station on the ground level on the east side of the terminal. A one-way fare is $2.50.
Thinking about a move near the airport? Search Salt Lake City homes, explore living in Salt Lake City, learn about buying with Red Sign or selling, or connect with an agent. Since 2008, Red Sign Real Estate Team has helped with about 3,500 transactions and earned 1,950+ five-star reviews.
Sources: Salt Lake City International Airport, SLC International Airport to Mark Completion of The New SLC (July 23, 2026) and Touch Down: SLC International Airport Celebrates the End of an Era (Oct. 24, 2026); The New SLC fact sheet, public transportation and parking pages (accessed Oct. 27, 2026); KUTV, Oct. 24, 2026; Utah Inland Port Authority, Rail Project to Reduce West Side Crossing Delays (May 21, 2026) and Northwest Quadrant study.
Red Sign Team